"Working airside means every step is planned before we arrive. Doing every aspect of the design and manufacture in our factory is what let us install the shelter quickly and safely."
John Ford - ENCAT Engineer and Director
Ward Civil needed a storm shelter for the workers on the airside apron at Sydney Airport, Mascot, as part of the works they were delivering there. The shelter gives ground staff somewhere to take cover when a storm comes over, close to where they work and park their vehicles.
ENCAT certified the design, manufactured the shelter in our Wollongong factory, then delivered and installed it airside, all within a four week lead time.
This case study covers how the shelter was designed and built, how we worked within airside security rules, and what to send us if you need a shelter of your own.
Project at a glance
Item | Detail |
|---|---|
Client | Ward Civil |
Site | Sydney Airport, airside, Mascot NSW |
Purpose | Storm protection for airside workers |
Design | Ward Civil in collaboration with Sydney Airport |
Design certification | ENCAT |
Scope | Certification, manufacture, delivery and installation |
Quantity | 3 x shelters |
Size | 5.2 m x 2 m x 3 m high |
Weight | 600 kg |
Frame | Galvanised steel |
Finish | Zinc-rich primer and powder coated top coat in Surfmist |
Walls and roof | Perforated metal sheeting |
Design wind speed | 46 m/s (ULS), 37 m/s (SLS) |
Lead time | 4 weeks from order to installation |
Time on site | 1 hour |
Installed | October 2026 |
Project value | $70,000 |
Why airside workers need a storm shelter
In short: the apron is open ground with no natural cover, so workers need a safe shelter close to where they work when a storm arrives.
Ground staff on an apron work in the open, often a long walk from the terminal. When a storm comes through they need cover that is close by and built for the conditions.
Anything installed airside has to be robust and well fixed. A loose panel or fixing near aircraft is a hazard, so the build quality matters as much as the cover the shelter provides.
Designed with Sydney Airport, certified by ENCAT
In short: Ward Civil and Sydney Airport designed the shelter together. ENCAT certified the design and manufactured it.
The design was a collaboration between Ward Civil and Sydney Airport, and Ward Civil supplied the drawings. ENCAT completed the design certification. Before cutting any steel, we reviewed the drawings for fabrication and checked how the shelter would be lifted, transported and fixed down.
The shelter was designed, engineer certified and manufactured to:
- AS 1170.0:2002 Structural design actions, Part 0: General principles
- AS 1170.1:2002 Structural design actions, Part 1: Permanent, imposed and other actions
- AS 1170.2:2002 Structural design actions, Part 2: Wind actions
- AS 4100:1998 Steel structures
- Design wind speed of 46 m/s (ULS) and 37 m/s (SLS)
These were the standards specified for this project. We can design, certify and manufacture to whatever standard your project specifies, including new editions as standards are revised and updated.
Manufactured in our Wollongong factory
In short: every step of fabrication and finishing was done under one roof in our Unanderra factory.
All fabrication was done in our Unanderra factory in Wollongong:
- Cutting: frame members were cut on our tube laser, so every part matches the drawing.
- Welding: welded by qualified welders to AS/NZS 1554.1.
- Corrosion protection: galvanised steel, then a zinc-rich undercoat and a Surfmist powder coat top coat. Airports are open, exposed sites, and the two-coat system is there for a long service life.
- Assembly: the shelter was fully assembled in the factory, so installation was quick and simple: drill the concrete, set the chemical anchors and bolt the shelter down.
A four week lead time
In short: in-house fabrication and finishing removed the waiting time between suppliers.
Ward Civil needed the shelter on site within four weeks. Because cutting, welding, powder coating and assembly all happen under one roof, there was no waiting on outside suppliers between steps. Fabrication was complete within two weeks, and powder coating took one day.
Installing airside at an operating airport
In short: the shelter arrived assembled and was craned into place in one hour, with airport security and safety rules followed throughout.
Working airside is not like a normal civil site. Every person and vehicle goes through security screening, and the work has to fit the time window the airport sets. All of our personnel and vehicles passed the airport’s security requirements.
We planned the installation so the time on the apron was as short as possible:
- The shelter was delivered fully assembled on our crane truck. It weighs 600 kg.
- It was lifted straight onto its prepared concrete slab.
- The base was fixed with chemical anchors. Holes were drilled with dust extraction, which keeps dust and debris off the apron, where loose material is a hazard to aircraft.
- The work area was kept inside water-filled barriers throughout.
- The installation took one hour.
Before the lift, we completed a lifting permit for the airport. It covered the service records and load charts for our Hiab crane, the lifting points on the shelter, the slings and chains we would use, and how they would be attached while the shelter sat on the back of the truck.
What this means for your project
Procurement officers: we manufacture to your drawings or design to your brief, certify to the standards your project specifies, and can work to short lead times because the work stays in our factory.
Civil contractors: shelters arrive assembled and ready to lift, which keeps your site program and crane time short.
Councils and asset owners: galvanised steel with a zinc undercoat and powder coat gives a long life with little maintenance.
Safety officers: we work to strict site rules, including airside security and lifting permits, and we plan installations to keep time on site to a minimum.
What we need to quote a storm shelter
To quote a storm shelter we need:
- Drawings, or the size and number of shelters you need
- Where it will go and how exposed the site is, e.g. inland, coastal or airport
- The weather it needs to protect against
- Colour and finish
- Footings: a new slab or an existing one
- Site access and any security or induction requirements
- Supply only, or supply and install
We have been designing, manufacturing and installing steel infrastructure since 1989. A related example is the bus shelters we installed at Sydney Airport’s T3 Domestic Terminal.
Frequently asked questions
Can ENCAT manufacture a shelter to our own drawings?
Yes. This shelter was designed by Ward Civil in collaboration with Sydney Airport, then certified and manufactured by ENCAT. We can also design a shelter to your brief.
What standards was the storm shelter certified to?
It was designed, engineer certified and manufactured to AS 1170.0, AS 1170.1, AS 1170.2 and AS 4100, for a design wind speed of 46 m/s (ULS) and 37 m/s (SLS). We can work to whatever standard your project specifies.
How long does it take to make a storm shelter?
This job took four weeks from order to installation. Fabrication took two weeks and powder coating one day. Lead time depends on the design and the number of shelters.
Can ENCAT install on an airport or other secure site?
Yes. We installed this shelter airside at Sydney Airport in one hour, after our personnel and vehicles passed the airport’s security requirements and we completed a lifting permit.
What finish is used for outdoor steel shelters?
We used galvanised steel with a zinc-rich undercoat primer and a powder coated top coat in the client’s colour, Surfmist, for long life on exposed sites.